Roadstock: Eldorado & Virginia Pkwy Tour

Concrete Panel Replacement Project

Eldorado and Virginia Streets will be under construction for concrete panel replacements.

This project will replace damaged concrete panels and strip the roadway to improve the overall driving surface along Eldorado Parkway and Virginia Parkway.

  • Eldorado Parkway | Ridge Road to U.S. 75
  • Virginia Parkway | Stonebridge Drive to U.S. 75

One-mile segments will be completed before starting the next phase of the project.

Frequently Asked Questions

City of McKinney Public Works


Phases

Phases overview
Phase 2: Virginia Parkway: Stonebridge Dr. to Hardin Blvd.
Virginia Parkway: Stonebridge Dr. to Hardin Blvd.
Phase 3: Virginia Parkway: Hardin Blvd. to U.S. 75
Virginia Parkway: Hardin Blvd. to U.S. 75

Eldorado Parkway

June 23, 2025 5:00 AM - May 31, 2026 4:59 AM

Eldorado Parkway | Late June 2025 - May 2026

The project started the week of June 23 and was expected to last 12 – 18 months, weather permitting. Panel construction is complete while striping and landscaping remain. The project was divided into 4 phases, including:

  • Ridge Rd. to Lake Forest Dr.
  • Lake Forest Dr. to Hardin Blvd.
  • Hardin Blvd. to Country Club Dr.
  • Country Club Dr. to U.S. 75